Contingency: definition and worked example
Contingency covers the unforeseen costs of a build: worse ground than expected, a rise in a material price, work that must be redone, bad weather. The contingency allowance is the percentage added to the quote to absorb them without stopping work.
Also called : contingency allowance, aléas.
In practice
It is not a margin for the contractor: it is a reserve for the owner. A budget worked out to the last unit is not a rigorous budget, it is one that stops at the first surprise — and a stopped site costs more than a provisioned one.
The right rate depends on what is known: the more precise the drawings and the soil study, the lower it can be. In the app the contingency rate is set in the quote settings; it is zero by default, so it is yours to set.
Worked example: the 3-bedroom house of 115 m²
On the 3-bedroom house, contingency applies to the total of materials and labour, before taxes. With a 10% allowance the pre-tax total rises by 10% — and the taxes, calculated on it, rise by as much. In the app this rate is zero by default: it is yours to set, according to what you know of the ground and how precise your drawings are.
Quantities computed by the SangoImmo engine on the 3-bedroom house model — the one the app opens. No price is given: it depends on your region, and you are the one who enters it.
Not to be confused with
Not to be confused with the contractor's margin (their pay) nor with extra work you decide on during the build: those are choices, not contingencies.
Frequently asked questions
- What percentage should I allow for contingency?
- There is no universal rate: it depends on how precise the drawings and the soil study are. What matters is to allow one on top of the quote: in the app the rate is zero until you set it.
Sources and references
- Quantities and areas: computed by the SangoImmo engine from the model itself — see the methodology. Drawings and figures are reusable under CC BY 4.0.
- Prices: none are published here. What a house costs depends on where it is built; in the app you enter the prices, taxes and rules of your own region.
- Building rules differ from one place to another: check a plan with the competent authority where you build before you start.
See these words on your own house
Draw your plan: the 3D view, the takeoff and the quote are computed from the same model, at your own prices.
Launch SangoImmo — freeor try the quantity calculators