A free construction quote template — and a genuinely costed example

A clear quote wins the job; a vague one loses it. Here is the construction quote template we use, free to download and fill in — plus a complete worked example costed by the SangoImmo engine on a real 3-bedroom house.

Download the template

Free, no signup, no email required. Reuse it for your own jobs, including commercially.

What a construction quote must contain

Most quotes that get rejected are not too expensive — they are impossible to check. A client who cannot see what they are paying for assumes the worst. A quote that wins reads like an audit trail:

What a complete quote looks like (real example)

This is not a mock-up. It is the SangoImmo engine's own bill for the published 3-bedroom house plan — 80 priced lines, 115 m², at 2026 Cameroon catalogue prices.

Floor plan of the 3-bedroom house used in the worked quote example, 115 m².
Every quantity in the example quote is measured off this plan — that is what makes the numbers checkable rather than assumed.
Worked example — 3-bedroom house, 115 m²
SectionDescriptionQtyUnit priceTotal
FoundationsLean concrete5,76 m³95 000 FCFA500 000 FCFA
FoundationsStrip footing (reinforced)5,18 m³165 000 FCFA900 000 FCFA
FoundationsFoundation block 20cm34,56 m²14 500 FCFA500 000 FCFA
FoundationsBottom tie beam (RC)43,2 ml8 500 FCFA400 000 FCFA
FoundationsCompacted laterite fill17,28 m³12 000 FCFA200 000 FCFA
MasonryHollow block 20 cm1247 u500 FCFA500 000 FCFA
MasonryHollow block 15 cm1479 u500 FCFA500 000 FCFA
MasonryCement render (both faces)414,22 m²3 500 FCFA1 400 000 FCFA
MasonryCement CEM II (50 kg bag)163 sac6 000 FCFA1 000 000 FCFA
MasonryRiver sand7,51 m³14 000 FCFA100 000 FCFA
MasonryCrushed gravel 5/157,65 m³22 000 FCFA200 000 FCFA
MasonryRebar Ø8 (stirrups)111,13 kg1 000 FCFA100 000 FCFA
MasonryRebar Ø10111,13 kg1 000 FCFA100 000 FCFA
MasonryRebar Ø12148,18 kg1 000 FCFA100 000 FCFA
MasonryTop tie beam (RC)78,83 ml8 500 FCFA700 000 FCFA
MasonryRC post 20×2029,16 ml12 500 FCFA400 000 FCFA
FloorsConcrete slab 12 cm + mesh115,2 m²16 500 FCFA1 900 000 FCFA
FloorsSmooth cement screed115,2 m²4 500 FCFA500 000 FCFA
FloorsWood-look tile80,96 m²17 500 FCFA1 400 000 FCFA
FloorsPorcelain tile 40×4032,14 m²11 000 FCFA400 000 FCFA
FloorsTile adhesive (25 kg bag)37 sac6 500 FCFA200 000 FCFA
FloorsTile grout90,6 kg1 000 FCFA100 000 FCFA
FloorsTile skirting84,69 ml2 000 FCFA200 000 FCFA
CeilingPlastered + painted ceiling115,2 m²3 000 FCFA400 000 FCFA
Openings6 lines1 500 000 FCFA
Plumbing8 lines1 300 000 FCFA
Electrical7 lines700 000 FCFA
Finishes4 lines2 700 000 FCFA
Sitework & utilities5 lines600 000 FCFA
HVAC5 lines1 100 000 FCFA
Security5 lines100 000 FCFA
Solar power5 lines0 FCFA
Fence & exterior6 lines200 000 FCFA
Fees & permits5 lines2 300 000 FCFA
Materials23 100 000 FCFA
Labour7 200 000 FCFA
VAT (19.25%)5 800 000 FCFA
TOTAL incl. tax36 200 000 FCFA

The downloadable CSV contains all 80 lines with every quantity and unit price. Prices are the national 2026 catalogue — replace them with your own suppliers' before sending anything to a client.

Doing it automatically, from the plan

Filling this template by hand takes an evening, and the arithmetic is where quotes go wrong. SangoImmo does the same job from the drawing: sketch the plan (or pick one of the free plans), and the app measures the quantities, prices them at your rates, adds labour and VAT, and exports the quote as a PDF you can send on WhatsApp. Change a room and every number follows. Free to design and cost, works offline.

Build my quote in SangoImmo — free

Frequently asked questions

Is this quote template really free?
Yes — download it, use it, modify it, including for paid work. No signup, no email, no watermark.
Does it open in Excel?
Yes. It is a CSV file with a UTF-8 byte-order mark and semicolon separators, which is the combination Excel opens correctly on French and African locales. It also opens in LibreOffice, Google Sheets and mobile spreadsheet apps.
What percentage should I add for labour?
On the projects this engine costs, labour runs about 35% of the materials total, but it varies by trade and by city. Show it as its own line rather than folding it into unit prices — clients trust a quote they can take apart.
How do I avoid quoting too low?
Quantities are where money is lost, not unit prices: an underestimated wall area costs you the same margin twice, in materials and in labour. Measure off a plan rather than from memory, add a contingency line, and state your exclusions.