HomeConstruction costs › Budget breakdown by item
By the SangoImmo team·Updated
Budget · Cameroon · 2026

Construction budget breakdown by item in Cameroon

On a standard 138 m² villa, materials break down first across masonry, floors, foundations. Labour is about 35% of the materials cost and 19.25% VAT adds to the total.

Materials cost by item

Example of a 4-bedroom 138 m² villa (estimated total 38 800 000 FCFA incl. tax):

Materials by item — 138 m² villa
ItemMaterials (FCFA)Share
Masonry5 750 000 FCFA23 %
Floors5 250 000 FCFA21 %
Foundations3 000 000 FCFA12 %
Finishes2 750 000 FCFA11 %
Fees & charges2 250 000 FCFA9 %
Doors & windows1 300 000 FCFA5 %
Plumbing1 150 000 FCFA5 %
HVAC1 050 000 FCFA4 %
Electrical750 000 FCFA3 %
Earthworks & utilities700 000 FCFA3 %
Ceiling450 000 FCFA2 %
Fencing & exterior200 000 FCFA1 %
Security100 000 FCFA0 %
Total materials24 750 000 FCFA100 %

Shares computed on the materials cost (SangoImmo engine, 2026 catalog). Labour (≈ 35%) and VAT (19.25%) then apply to the whole. Excluding land, servicing and contingencies.

How to read these items

For unit prices, see the materials prices guide; for cost by house type, the construction cost guide.

Frequently asked questions

How does a house construction budget break down in Cameroon?
On the materials cost, the heaviest items are masonry, floors, foundations. Labour (≈ 35% of materials) and VAT (19.25%) add on top.
Which item costs the most in a build?
Masonry (blocks, cement, steel, mortar) is usually the top materials item, followed by floors/tiling and foundations.
How do I see the exact breakdown for my plan?
SangoImmo details the quote item by item from your plan, and you can adjust each price. Free, offline.

Sources and references

See your project breakdown

SangoImmo details your quote item by item from your plan — free, offline.